Migration Guide: spec.md Project/Board Fields (v0.31.0)
Version: 0.31.0 Date: 2025-12-04 Related ADR: ADR-0190
Overview
Starting with v0.31.0, SpecWeave requires explicit project (and board for 2-level structures) fields in spec.md YAML frontmatter. This ensures increments sync to the correct location in living docs.
Who Needs to Migrate?
Check Your Structure Level
Run this to detect your structure level:
# Check if you have ADO area path mapping (2-level)
jq '.sync.profiles | to_entries[] | select(.value.provider == "ado") | .value.config.areaPathMapping.mappings' .specweave/config.json
# Check if you have JIRA board mapping (2-level)
jq '.sync.profiles | to_entries[] | select(.value.provider == "jira") | .value.config.boardMapping.boards' .specweave/config.json
# Check if multiProject is enabled (1-level)
jq '.multiProject' .specweave/config.json
Migration Requirements
| Structure | Required Fields | Migration Urgency |
|---|---|---|
| Single-project (default) | None (optional) | Low - warning only |
| multiProject enabled | project: | Medium - recommended |
| ADO area paths | project: + board: | High - REQUIRED |
| JIRA boards | project: + board: | High - REQUIRED |
| Umbrella with teams | project: + board: | High - REQUIRED |
Migration Steps
Step 1: Find Increments Without Project Field
# List all spec.md files without project field
for f in .specweave/increments/*/spec.md; do
if ! grep -q "^project:" "$f"; then
echo "Missing project: $f"
fi
done
Step 2: Identify Available Projects/Boards
# List available projects
ls -la .specweave/docs/internal/specs/ | grep -v "^total" | grep "^d"
# For 2-level, list available boards per project
for p in .specweave/docs/internal/specs/*/; do
echo "Project: $(basename $p)"
ls -la "$p" | grep -v "^total" | grep "^d" | grep -v "FS-"
done
Step 3: Add Project Field to spec.md
For 1-level structures:
---
increment: 0001-my-feature
project: my-project # ADD THIS LINE
title: "My Feature"
status: active
---
For 2-level structures:
---
increment: 0001-my-feature
project: acme-corp # ADD THIS LINE
board: digital-operations # ADD THIS LINE
title: "My Feature"
status: active
---
Step 4: Verify Migration
# Re-run check to ensure all increments have project field
for f in .specweave/increments/*/spec.md; do
if ! grep -q "^project:" "$f"; then
echo "Still missing project: $f"
fi
done
# For 2-level, also check board field
for f in .specweave/increments/*/spec.md; do
if ! grep -q "^board:" "$f"; then
echo "Missing board (may be needed): $f"
fi
done
Step 5: Test Sync
/specweave:sync-specs
Automated Migration Script
Save this as migrate-project-fields.sh:
#!/bin/bash
# Migration script for adding project/board fields to spec.md
PROJECT="${1:-default}" # Default project name
BOARD="${2:-}" # Optional board name (for 2-level)
for spec_file in .specweave/increments/*/spec.md; do
if grep -q "^project:" "$spec_file"; then
echo "SKIP: $spec_file (already has project)"
continue
fi
# Find the line after 'increment:' to insert project
if [ -n "$BOARD" ]; then
# 2-level: add both project and board
sed -i.bak '/^increment:/a\
project: '"$PROJECT"'\
board: '"$BOARD" "$spec_file"
else
# 1-level: add only project
sed -i.bak '/^increment:/a\
project: '"$PROJECT" "$spec_file"
fi
echo "UPDATED: $spec_file"
done
echo ""
echo "Migration complete! Verify with:"
echo " grep -l 'project:' .specweave/increments/*/spec.md | wc -l"
Usage:
# 1-level migration
./migrate-project-fields.sh my-project
# 2-level migration
./migrate-project-fields.sh acme-corp digital-operations
Troubleshooting
Error: "Missing 'project:' field in spec.md"
Cause: Your spec.md doesn't have the required project: field.
Solution: Add project: <project_name> to YAML frontmatter.
Error: "Missing 'board:' field in spec.md (2-level structure)"
Cause: You have ADO area paths or JIRA boards configured, requiring both project and board.
Solution: Add both project: and board: to YAML frontmatter.
Warning: "No 'project:' field in spec.md"
Cause: Your 1-level structure increment doesn't have explicit project field.
Impact: Sync will use auto-detection (deprecated). Add project field for deterministic behavior.
Legacy Project: Field
If your spec.md has **Project**: my-project in the body (not frontmatter):
- This is still supported but deprecated
- You'll see a warning suggesting migration to YAML frontmatter
- Migration is recommended for consistency
New Increment Workflow
After v0.31.0, the increment planner automatically prompts for project/board:
🔍 Detected 2-level structure (ADO area path mapping)
Available projects: acme-corp
📁 Project: acme-corp
Boards: clinical-insights, platform-engineering, digital-operations
Which board should this increment sync to?
> digital-operations
✅ Increment will sync to: internal/specs/acme-corp/digital-operations/FS-XXX/